The dispatch lab
A small, fictional grid. Power is in GW; energy offers and nodal prices are in $/MWh.
Start with a case
Each hour is a separate snapshot. Play does not simulate a continuous operating trajectory.
Drag the slider or the red line in the supply chart.
- System demand
- Dispatchable headroom
- Output slack; network delivery not checked
- West reference price
- $/MWh · losses omitted
- Metro price
Supply and dispatch
Block width is available output; height is the energy offer. Green shows accepted output. Network and ramp constraints can make a higher-cost block run before a cheaper one is full.
Select an offer block to inspect its output bounds, or use the table below.
Resource dispatch and limits
| Resource | Offer $/MWh | Range GW | Output GW |
|---|
Flows and nodal prices
Both views use the same dispatch. The outage check requires it to respect limits before and after the line is removed, without corrective redispatch. Switching views changes the drawing, not the price calculation.
Prices are the marginal cost of one more MWh at each bus. Outage flows are recomputed on the changed topology.
Bus prices and line flows
Net injection includes any load reduction. Positive line flow goes from the first named bus to the second.
| Bus | Load GW | Net injection GW | Price $/MWh | Congestion $/MWh |
|---|
| Line | Flow GW | Limit GW |
|---|
The commitment schedule
An illustrated schedule, not the result of a unit-commitment optimization.
Select a cell, or use arrow keys within the schedule, for resource and hour details. The outlined column is the selected delivery hour.
What the model includes, and what it leaves out
The dispatch calculation
Minimize energy offer cost and any emergency curtailment penalty subject to power balance, resource output bounds, and linear DC branch limits. Curtailment reduces load at its own bus. Demand response is a paid reduction in Metro load, represented as an equivalent injection.
min Σ cᵢPᵢ + 600 Σ sᵦ
qᵦ = Σᵢ at bus b Pᵢ + sᵦ − dᵦ
Σ qᵦ = 0 · |Hᵏq| ≤ Fᵏ
Pᵢ,min ≤ Pᵢ ≤ Pᵢ,max · 0 ≤ sᵦ ≤ dᵦ
P is resource dispatch, d is requested load, s is emergency load curtailment, and q is net bus injection. H maps injections to branch flows; k indexes the intact grid and, when enabled, the selected outage. One GW sustained for one hour is 1,000 MWh, so multiplying this objective by 1,000 gives the cost of the one-hour snapshot in dollars. Prices are reported in $/MWh.
In the real-time example, Pmin = max(online minimum, prior output − ramp × Δt) and Pmax = min(available capacity, prior output + ramp × Δt). Ramp rates are fictional GW/hour values and Δt = 1 hour. Real systems dispatch on a much shorter interval; PJM’s real-time energy market uses five minutes. The prior output is calculated independently from the previous hour’s intact-grid intraday example and stays fixed while you change demand or the outage check. Startup and shutdown trajectories are omitted.
The outage check removes the South–East line and recomputes all remaining flows. It checks that selected contingency, not every possible N-1 outage. Dispatchable headroom is unused output capability, excluding wind and solar; it is neither a reserve award nor a guarantee that extra power can be delivered through the network.
Nodal prices come from the dispatch problem’s linear-programming duals: the marginal offer cost of serving extra demand at each bus with commitment, availability, and ramp bounds held fixed. The energy/congestion split uses West as the reference bus; the total nodal price does not depend on that reference. At a change in the active constraints, a marginal price can be nonunique.
The illustrations
Day-ahead and intraday schedules are prescribed examples. There is no mixed-integer commitment solve, reserve co-optimization, or state-estimation calculation. Minimum up/down times and startup costs are not enforced. The state-estimation tab explains the measurement workflow; its dispatch example uses the same inputs as the intraday tab.
Losses, reactive power, voltage limits, storage energy balance, and market settlement rules are omitted. Storage is a discharge block, so playing hours does not charge or deplete a battery. Releasing fast-start blocks is a manual commitment change for the current snapshot, not an optimized start decision. The fleets, offers, ramp rates, and curtailment penalty are fictional. Actual processes and fast-start rules vary by market.
Further reading: PJM energy markets, MATPOWER’s DC optimal power flow, and DC transfer factors.